Connie and I have finally decide to build our great big house on the Colorado River in Bullhead City, Arizona.  This site was created to share with our friends and family the progress of that build and then the final product.

We have chosen a friend and Contractor, Mike Evans, of ELE Construction to help build the house for us.  Of course, Mike will be getting a lot of help from Mac......

 

What's  New

  • New  Pictures Added to the Pictures Page 6/20/09

Plan Survey

Key Milestones - Updated

  • August 30 - Final Sign-off
  • June 30 - Install Patio Doors
  • June 19 - Finish Drywall
  • June 12 - Finish Insulation
  • March 31 - Finish Rough in Electric and Plumbing
  • March 29 - Finish Rough in Low Power
  • February 7 - Start Low Voltage Stuff
  • February 5 - Start Electrical, Plumbing
  • February 2 - Start Mechanical
  • January 7 - garage Floor Slab Poured
  • December 4 - Top Floor Framed and Trusses Installed
  • November 14 - 2nd floor trusses to be installed
  • October 31 - Garage Foundation to be Started
  • October 24 - First Floor Trusts to be Installed
  • October 17 - Start Framing of Basement
  • October 8 - Snap out wall layout in Basement
  • October 6 - Install back wall of basement
  • October 3 - Finish Basement Cement work
  • September 29 - Start Foundation for Basement
  • September 26 - Retaining Wall Complete
  • September 19 -  Retaining wall started!
  • more ...
House Input

Home | Documents | Discussion | Schedule | Search | Contact Information
Counter
 Copyright River Rat Racing 2008
For problems or questions regarding this Web site contact admin@morrisriverlodge.com.
Last updated: 06/14/09.